LETHABONG HEKPOORT COMMUNITY PROJECT



Installation Details

  • 3 Phase OFF Grid Power Plant to run 5 x JORA Composters. Each composter utilizes 1 x 1.5kW Shredder, 2 x 0.75kW rotary motors, Fan and PLC board.
  • Plant would also provide the community with external lighting and flood lights for the new entertainment park.
  • The design included 15 x 4kW Axpert Inverters in pairs of 6 units x 2 for 3phase solution and 3 units x 1 for 3 phase solution.

Lethabong slideshow

Slide background

Installation In Progress

Slide background

12 x 4kW Axpert Inverters

Slide background

Where Art and Technology Collide

An awesome project that was developed for the local community.
The main river of this project was the installation of Solar Powered Urine Divertion (SPUD) composting toilets.
The project required the installation of 500 toilets which would include the neccesary waste management and composting
of the waste from these toilets. The waste management is done with 5 x JORA composters powered by the PV
power plant of size 60kWe.